Oct. 02, 2015

Building 5

Weather - Rain

No work


Oct. 01, 2015

Building 5

Weather - cloudy with rain coming in at 5pm

Ripped the front side of units 506, 508 & 510

Moved all lightweight materials to areas on the roof where the wind would not affect them.

Additional work:

Replaced rotted siding on two sides of the small dormers on unit 510

____________ lnft.

Replaced one corner post on one dormer on unit 510 (4 lnft).

 


SEP. 30TH, 2015

Building 5

Weather - Rain

No work

Port-A-Potty was delivered

 


SEP. 29TH, 2015

Building 5

Weather - mostly cloudy (started raining at 5pm)

Replaced the roofs on the backside of units 502 & 504.

Worked on two (2) tunnels following GAF specifications.

Met with gutter foreman to review the scope of work.

Additional work:

Replaced rotted siding on the rear corner of the dormer on unit 502 ___lnft

Replaced rotted siding on the inside corner of a dormer  ______ lnft.

Replaced one corner post on unit 502 (4 lnft.).

 


SEP. 28TH, 2015

Building 5

Weather - overcast with occasional sun

Loaded roofs and replaced to front portion of the roof on units 502 & 504.

 

Additional work:

Replaced 3’ of 1” x 8” rake board

Replaced _____’ of decorative trim

 


Want To See Work From a Previous Week? Click On a Button Below.