WEEK 2 10/05-10/10


Oct. 10 2015

Building 4&5

Weather - Sunny

Ripped the front of units 401 & 403.

Started installing trim on the front of unit 502.

 

 

 


Oct. 09 2015

Building 4

Weather - Rain

Loaded building 4

 

 

 

Oct. 08 2015

Building 5

Weather - Sunny

Ripped the entry roofs on units 502 and 516.

Finished the shingles over units 506, 508, 510, 512 and 514.

Worked with Nelson on the tunnels over unit 514.  Photographed the entire process.

Pierced refrigerant line over unit 514.

Worked with HVAC company to get the refrigerant lines repaired in units 510 and 514.  Unit 510 was repaired from the inside and unit 514 was repaired from the roof.

The sheetrock in both units needs to be replaced and painted.


Oct. 07 2015

Building 5

Weather - Sunny

Ripped the back side of units 506, 508 & 510.

Met with Joe (unit 514) to review the scope of work for his 2 tunnels.

Joe requested that his existing 2x3 leader be upgraded to a 3x4 leader.

Met with gutter foreman to finalize a Tuesday start date.

Pierced the refrigerant line over unit 510.  HVAC company was called to resolve issue.

 

 

 


Oct. 06 2015

Building 5

Weather - Sunny

Ripped the back side of units 512, 514 & 516

KJB Fireplaces started to replace the chimney caps on units 502 & 504.  Met with Ken Belanus, owner of KJB Fireplaces, to review scope of work and establish timeline.

 

 


Oct. 05 2015

Building 5

Weather - Partly sunny

Ripped the front of units 512, 514 & 516.

Installed metal pan at the bottom of the valley over unit 512.

Removed 1 sheet of plywood over unit 514. Shaved down sheet rock in order to eliminate the bumps in the plywood. Re-installed plywood.

Additional work:

Rotted rake and trim at the bottom of the valley of unit 512 (            lnft).

Rotted siding along the entire side of unit 510 (         lnft).

Rotted siding along the entire side of unit 514 (         lnft).

 